How to Write a Millwork RFI That Gets a Fast, Useful Answer

A millwork RFI gets a fast answer when it covers one issue, cites the exact sheet, detail, specification section and revision, asks a question that can be answered in one line, proposes a resolution with a reason, and states the date a response is needed. Send it through the general contractor, log it, and hold the affected drawings until it is resolved.
- Routing
- Shop to general contractor to architect, and back the same way
- A strong RFI
- One issue, exact references, a proposed answer, a required-by date
- Best timing
- At kickoff, before the affected sheets are drawn
A request for information (RFI) is the formal way a millwork shop asks the design team to clarify the contract documents. Written well, it settles an ambiguity before it turns into a rejected submittal or a re-cut part. Written badly, it sits in a queue while your drafting and your floor wait.
Why the RFI matters
An RFI puts a question, and its answer, on the project record. When a drawing and a specification disagree, when a dimension is missing, or when a detail cannot be built as drawn, the RFI is how you get a written direction instead of a verbal one that nobody remembers at closeout.
On a typical commercial project the millwork shop is a subcontractor, so the RFI does not go straight to the architect. It goes to the general contractor, who reviews it, may answer it directly if the documents already cover it, and otherwise forwards it to the architect or the relevant consultant. The answer comes back down the same chain. Two practical consequences follow:
- Every RFI has at least two readers. The GC's project engineer has to understand it well enough to route it, and the architect has to understand it well enough to answer it.
- The response clock is set by the contract, not by habit. Allowed response times vary from project to project. Check your subcontract and the project's Division 01 requirements for the stated review period, and plan your drafting schedule around it.
It also helps to be clear about what an RFI is not. It is not a substitution request, which normally has its own form and approval path. It is not a change order, although an answer can lead to one. And it is not a submittal: shop drawings show how you intend to build the work, while an RFI asks what the documents require.
When to raise an RFI and when not to
The cheapest time to ask is before the affected sheets are drawn. A disciplined shop reads the full set once at kickoff, lists every open question, and sends the RFIs that week. Typical millwork triggers include:
- Conflicts between documents. An elevation tags a wood veneer while the finish schedule lists plastic laminate, or a detail shows one edge profile and the specification calls for another.
- Missing information. No overall dimension on a run of casework, no section through a reception desk, no hardware called out for a specialty door, or no quality grade named for the woodwork.
- Details that cannot be built as drawn. A panel larger than the available sheet size with no joint shown, a countertop span with no support, or a scribe condition with no allowance.
- Coordination gaps. Appliances, sinks, lighting, or power in the millwork with no model numbers or cutout sizes, or blocking that the drawings do not assign to anyone.
- Field conditions. Measured dimensions that differ from the architectural drawings enough to change the design.
Do not send an RFI for something the documents already answer. Questions about your own means and methods, such as how you join a carcass, usually belong in the shop drawings, where the architect reviews your proposed construction. If the bid documents are unclear before award, use the pre-bid question process and its deadline, as covered in our guide to winning more millwork bids.
Reference the exact document
The reviewer should be able to find what you are looking at in under a minute. Cite the sheet number, the detail or elevation number, the room name and number, the specification section and paragraph, and the revision or addendum you are working from. Attach a marked-up snip of each reference with the conflict clouded.
Compare two openings. "What finish do you want on the reception desk?" forces the reader to work out which desk, which surface, and why you are asking. "Elevation 3/A-402 tags the reception desk front panels WD-1; the finish legend on A-601 lists the same desk as PL-2" tells the reader the problem and where to look. Specification references should be just as exact. Architectural woodwork is normally specified in MasterFormat Division 06, for example Section 06 41 00 for architectural wood casework, while manufactured casework often sits in Division 12. Name the section and paragraph you read, not simply "the spec."
Ask one clear question
One RFI, one issue. Five unrelated questions in a single RFI usually produce three answers and a second round, and the RFI cannot be closed in the log until the slowest item is resolved.
Phrase the question so it can be answered in a line: yes or no, option A or option B, or a single value. "Please advise" is not a question. "Which finish applies to the front panels, WD-1 or PL-2?" is.
Put the question in the subject line as well. Many reviewers triage from a log view that shows only the number and the title, so "RFI 014: Reception desk front panel finish, WD-1 vs. PL-2" gets handled faster than "Millwork question."
Propose your answer
The fastest RFIs carry a proposed resolution. Designing a fix takes the architect time; confirming a sensible one takes minutes.
A useful proposal has three parts:
- The recommendation. State exactly what you would build, with material, thickness, and location.
- The reason. Tie it to the documents or to a recognized standard: consistency with the adjacent paneling, the governing specification paragraph, or the requirements of the Architectural Woodwork Institute standard the project references.
- The impact. Say whether the answer could affect cost, lead time, or other trades, and reserve your position in whatever way your contract requires. An RFI response clarifies the documents. It does not by itself change the contract sum or schedule, so if the answer adds scope, follow the change process in your subcontract promptly.
Add the date you need the answer by and what it is holding up. "Response needed by the 14th to hold the casework submittal date" is specific, and it documents the schedule effect if the answer arrives late.
A weak RFI and a strong one
Here is the same question written two ways. The project details are illustrative.
Weak
Subject: Reception desk
The drawings are unclear on the reception desk. Please advise on materials and how you want it built so we can proceed.
The reader does not know which drawing, which part of the desk, what is unclear, or what answer would let you proceed.
Strong
Subject: RFI 014: Reception desk (Lobby 101) front panel finish, WD-1 vs. PL-2
Reference: Elevation 3/A-402 and finish legend on A-601, both dated per Addendum 2; Section 06 41 00, paragraph 2.2.
Condition: Elevation 3/A-402 tags the reception desk front panels WD-1 (wood veneer). The finish legend on A-601 lists the reception desk as PL-2 (plastic laminate). Section 06 41 00 does not address this desk specifically.
Question: Which finish applies to the front panels of the reception desk, WD-1 or PL-2?
Proposed resolution: Provide WD-1 veneer on the front panels to match the adjacent lobby wall paneling shown on 1/A-402. Transaction top and work surface to remain as drawn.
Impact: The two finishes differ in material cost and lead time. Shop drawings for the desk are on hold pending response; all other lobby millwork is proceeding. Response requested by [date] to maintain the submittal date of [date].
Attachments: Marked-up 3/A-402 and A-601.
The strong version can be answered with one word, and it leaves a record of what was asked, what was proposed, and when the answer was needed.
Track it to resolution
An RFI that is sent but not tracked is only slightly better than one that was never written. Keep a log, in a spreadsheet or in the GC's project management platform, with at least these fields:
- RFI number and short title
- Drawing and specification references
- Date sent and date the response is required
- Who currently holds it (GC, architect, or consultant)
- Date answered and a one-line summary of the answer
- Sheets in your shop drawing set that the answer affects
- Cost or schedule impact, and whether notice has been given
Review the log weekly and follow up on anything past its required date through the GC, in writing. If the schedule forces you to draft before an answer arrives, proceed on a stated assumption: note it on the affected sheet, reference the open RFI number, and tell the GC in writing what you assumed.
When an answer comes back, update the drawings and cite the RFI number in the revision note or on the detail, so the approved set carries its own trail. Open and answered RFIs should be reconciled against the set before it goes out, which is one of the items on our commercial millwork submittal checklist. Unresolved questions are also a common reason sets come back, as described in five submittal mistakes that get packages kicked back.
If an outside drafter produces your shop drawings, decide at kickoff who writes RFIs and who sends them. A drafting partner normally has no contractual relationship with the GC, so the usual arrangement is that the drafter flags and drafts each question and the shop issues it under its own number. When you evaluate a drafter, ask how open questions are handled before and during drafting; how Millmetric approaches a project is described on our process page.
Pre-send checklist
Before an RFI leaves the shop, confirm that it:
- Is not already answered in the drawings, specifications, addenda, or a previous RFI
- Covers one issue, with a subject line that states it
- Cites sheet, detail, room, specification section, and revision
- Asks a question that can be answered in one line
- Proposes a resolution and gives the reason for it
- States any possible cost or schedule impact
- Gives a required-by date and what the answer is holding
- Includes marked-up attachments
- Is entered in the RFI log before it is sent
Frequently asked questions
Who does a millwork subcontractor send an RFI to?
On most commercial projects the millwork shop sends the RFI to the general contractor, not directly to the architect. The GC reviews it, answers it if the contract documents already cover the question, and otherwise forwards it to the architect or consultant. The response returns through the GC. Your subcontract and the project's Division 01 requirements define the exact procedure.
How long does an architect have to answer an RFI?
There is no single universal deadline. The allowed response time is set by the project's contract documents and can differ from job to job. Check your subcontract and the Division 01 general requirements for the stated review period, state a required-by date in every RFI, and follow up in writing through the general contractor when that date passes.
What is the difference between an RFI and a submittal?
An RFI asks the design team to clarify what the contract documents require, for example which of two conflicting finishes applies. A submittal, such as shop drawings or samples, shows how you intend to meet those requirements and is reviewed for conformance with the design intent. Resolve RFIs first so the submittal does not carry open questions into review.
Does an RFI response authorize extra cost or time?
Not by itself. An RFI response clarifies the documents; it does not change the contract sum or schedule. If the answer adds scope or affects lead time, say so in the RFI, then give notice and request a change through the process and deadlines in your subcontract. Do not rely on the RFI response as approval of added cost.
Send the architectural drawings and specs. You get a fixed scope and price back within 24–48 business hours, before any drafting starts.
Get an Estimate →